EN TH

To be a leading value-oriented integrated energy company in Asia-Pacific

Slide Left Slide Right
No. Project Type Location Operator RATCH Group’s Equity Holding Fuel Type Total Installed Capacity (MW) PPA (Years) COD
1. Solarta Solar Power Generation Project (8 Projects)
  Sai Sena Solar Power Project VSPP Phra Nakhon Si Ayutthaya Solarta Company Limited 49% Solar Power 3.01 5 2011
  Sai Prapa, Sai Yai, Sai Thong and Sai Yoi Solar Power Projects VSPP Nakhon Pathom Solarta Company Limited 49% Solar Power 30.34 5 2012
  Sai Saphan 1&2 and Sai Tong Solar Power Project VSPP Suphan Buri Solarta Company Limited 49% Solar Power 8.96 5 2012
2. Solar Power Korat 3 Project VSPP Nakhon Ratchasima Solar Power (Korat 3) Company Limited 40% Solar Power 7.2 5 (Automatic Renewal) Mar. 2012
3. Solar Power Korat 4 Project VSPP Nakhon Ratchasima Solar Power (Korat 4) Company Limited 40% Solar Power 7.2 5 (Automatic Renewal) May. 2012
4. Solar Power Korat 7 Project VSPP Nakhon Ratchasima Solar Power (Korat 4) Company Limited 40% Solar Power 7.2 5 (Automatic Renewal) May. 2013
5. Huay Bong 2 Wind-Turbine Power Plant SPP Nakhon Ratchasima K.R. Two Co., Ltd 20% Wind Power 103.5 SPP Firm Contract, 5 years Feb. 2013
6. Huay Bong 3 Wind-Turbine Power Plant SPP Nakhon Ratchasima First Korat Co., Ltd 20% Wind Power 103.5 SPP Firm Contract, 5 years Nov. 2012
7. Songkla Biomass Company Limited Power Plant VSPP Songkhla Songkhla Biomass
Company Limited
40% Biomass from rubber wood 9.9 5 (Autometic Renewal) 9 Nov. 2015